|
By January 23, 13
hectares of land would have been reclaimed at Anse Aux Pins, which means
the creation of one of the two "islands" proposed in the
initial plan of the project, which also includes the creation of a
channel for fishermen.
The Anse Aux Pins
reclamation work, which started this week, is being carried out by UCPS
excavators as the dredger Vesalius
could not do the work on account of rough sea condition and a
breakdown in its auxiliary spud.
Meanwhile Vesalius'
contract comes to an end on January 30, when it will leave for Thailand
in a specialised vessel.
Speaking to the
press at the Anse Aux Pins site Thursday afternoon, Mr Patrick Lablache,
the special advisor in the Ministry of Land Use and Habitat, said Vesalius had on three occasions attempted to work at the site, but
had failed.
As a result, Mr
Lablache said, Vesalius had to
dig and pump up materials in the vicinity of the South East Island from
where they were conveyed via a two-kilometre long pipe running parallel
to the runway up to the site to be reclaimed.
According to Mr
Lablache around 26,000 cubic metres of materials are being pumped per
day.
In view of the fact
that Vesalius will be leaving
soon, Mr Lablache said it had to accelerate its work to continue
building up a stock of material to complete the project.
Reclamation of the
second "island", which will comprise some 9 hectares of land,
will be done by UCPS excavators using the material stockpiled by Vesalius. This work is expected to be completed in three years'
time.
Despite the delay in
the completion of the Anse Aux Pins reclamation project, Mr Lablache
noted that some of the infrastructural projects initially proposed would
still go on, such as the road to be constructed from Anse Faure up to
the district's children's playground.
Noting that this
project would be done in two stages, Mr Lablache said the first phase of
construction would end at the market and the second phase would complete
it.
A 100-metre wide and
10-metre deep channel for fishermen was initially proposed for the
project, but since the dredger has been unable to carry out the
excavation work at the site, Mr Lablache said the passage, which will be
dug out by the excavators, would now be smaller in size but would not
pose a problem to the fishermen since their boats would be able to
navigate through the channel quite easily.
He said work on the
channel would start in the next few weeks.
A representative
from the fishermen community at Anse Aux Pins, Mr Guy Esparon, who has
been working on board Vesalius to
oversee the reclamation work in progress, said it was understandable
that due to rough weather condition Vesalius
had not been able to work at the site but expressed hope that the
excavator would carry off the job successfully.
The reclamation at
Anse Aux Pins will provide more land for the industrial and commercial
activities, construction of a new school, recreational facilities and
health centre, as well as several other projects.
|